# core-v-wally Design Verification Test Plan
 | 
						|
 | 
						|
This document outlines the test plan for the Wally rv64gc configuration to reach Technology Readiness Level 5.
 | 
						|
 | 
						|
1. Pass riscv-arch-test
 | 
						|
2. Boot Linux
 | 
						|
3. FPU pass all TestFloat vectors
 | 
						|
4. Performance verification: Caches and branch predictor miss rates match independent simulation
 | 
						|
5. Directed tests
 | 
						|
	- Privileged unit: Chapter 5 test plan
 | 
						|
	- MMU: PMA, PMP, virtual memory: Chapter 8 test plan
 | 
						|
	- Peripherals: Chapter 16 test plan
 | 
						|
6. Random tests
 | 
						|
	- riscdv tests
 | 
						|
7. Coverage tests
 | 
						|
	- Directed tests to bring coverage up to 100%.  
 | 
						|
		- Statement, experssion, branch, condition, FSM coverage in Questa 
 | 
						|
		- Do not measure toggle coverage
 | 
						|
 | 
						|
All tests operate correctly in lock-step with ImperasDV
 | 
						|
 | 
						|
Open questions:
 | 
						|
1. How to define extent of riscdv random tests needed?
 | 
						|
2. What other directed tests?
 | 
						|
    PMP Tests
 | 
						|
    Virtual Memory Tests
 | 
						|
		How to define pipeline tests? 
 | 
						|
			Simple ones like use after load stall are not important.
 | 
						|
			Hard ones such as page table walker fault during data access while I$ access is pending are hard to articulate and code
 | 
						|
      Is there an example of a good directed pipeline test plan & implementation
 |